What happens when

Your renovation, step by step

Ten steps from the first phone call to the walk-through. For each one: what happens, what you need to do, and whether you can still use the room. Pick your room to see the steps that change.

  • Steps 1 to 4: planning, at your pace. The room still works.
  • Steps 5 to 9: on site. The room is out of action.
  • Step 10: it’s yours again
Which room?
  1. Planning

    You get in touch

    Call 0468 511 068, Monday to Friday, 9 am to 5 pm, or send the short form with a few details. If you’ve used the cost guide, your choices come with it.

    Your partRoughly what you’d like, your suburb, and whether it’s the only bathroom in the house.how you use the kitchen now.what the laundry has to fit.

    Room in use

  2. Planning

    A look at the room and a measure-up

    A visit to see the room, measure it properly and talk through what you want, what’s possible and roughly what it costs. It’s also when the floor, the walls and the waste are checked, because they decide what the new layout can do.The sink, the cooktop and the power points are noted, because moving them is what changes the price most.The taps, the waste and the machines’ sizes are noted, so the new cabinetry fits around them.

    Your partBe home for it. Photos or pictures of rooms you like help a lot.

    Room in use

  3. Planning

    Your quote

    A free quote for the work, so you can see what’s included before you decide. Any part that can’t be known until the walls are open, such as hidden rot, is talked through up front.

    Your partRead it, ask anything, and take your time.

    Room in use

  4. Planning

    Choices and a start date

    Tiles, vanity, tapware, toilet and glass are settled.Cabinet colours, benchtop, splashback, handles, sink and appliances are settled.Cabinet colours, benchtop, tub and tapware are settled. Then a start date is booked, with everything ordered in time.

    Your partMake your choices. Clear the bathroom cupboards before day one.Empty the cupboards and set up a spot to make a cuppa.Empty the cupboards and find a spot for the washing.

    Room in use

    Only bathroom in the house? Now is when how you’ll shower during the work gets planned, so it’s sorted before the strip-out.

    Still need to eat? Plan where the fridge, kettle and microwave will live for the weeks the kitchen is out.

  5. On site

    Protect and strip out

    Floors and the path in are covered, then the old room comes out: tiles, bath, vanity and fittings, back to the frame and the slab.cupboards, benchtops, splashback and old appliances.tub, cupboards and old tiles. The rubbish goes with it. In homes built before 1990, old sheeting is checked for asbestos first.

    Your partExpect noise and some dust for a day or two. Keep pets and little ones clear.

    Room out of action

  6. On site

    Frame, pipes and wiring

    With the walls open, the framing is checked, repaired and straightened, and noggins go in where cabinets, rails or a wall-hung vanity will hang. New pipes, wastes and wiring go where the new layout needs them, by licensed trades.

    Your partNothing, unless something unexpected turns up behind the wall. If it does, you’ll hear about it straight away.

    Room out of action

  7. On site

    Sheeting and waterproofingWalls patched and sheeted

    Wet-area board goes up, and the waterproof membrane goes on across the floor, up the walls and to 1800 mm in the shower. It has to cure properly before any tile goes near it.Wet-area board goes up where the tub and machines sit, and the floor and the wall behind the tub are waterproofed.New gyprock where the old cupboards came off, joints set and sanded, ready for paint and the new cabinetry.

    Your partNothing. This is the quiet stage.

    Room out of action

  8. On site

    TilingCabinetry and benchtopsCabinetry and tiling

    Floor tiles are laid to fall to the drain and the walls are tiled, with any niche set in. Then the grout, and silicone in the corners where it moves.The cabinets are set level and fixed, then the benchtop is measured off the cabinets themselves so it fits exactly. Stone and porcelain tops are made to that measure, which takes a little time.The cabinets go in level and the benchtop goes on, then the splashback and floor are tiled and grouted.

    Your partHave a look. It’s the stage when the room starts to look like the picture.

    Room out of action

  9. On site

    Fit-off

    The vanity, tapware, toilet, shower glass, mirror and towel rails go in, and the lights and fan are connected.The sink, tapware and appliances go in, the splashback goes up, and the doors and handles are fitted and adjusted.The tub, tapware and machines are connected, and the doors and handles are fitted and adjusted. Then the painting and the last touch-ups.

    Your partNot long now.

    Room out of action

  10. Done

    Clean, walk-through and handover

    The room is cleaned and you walk through it together: how things work, how to look after them, and anything you’d like adjusted. Based in Warana, so if something needs a look later, it isn’t far.

    Your partEnjoy the first shower.Cook something.Put a load on.

    Back in use

How long each step takes depends on the room and the choices. Your quote gives the timing for your job.

Questions

What people ask before they start

Do I need to move out?

Almost never for one room. The room being worked on is out of action, and there’s some noise and dust, but the rest of the house carries on.

What if it’s our only bathroom?

Say so when you get in touch. How you’ll shower while the work is on is planned at the choices stage, before anything comes out.

Who does the plumbing and electrical?

Licensed plumbers and electricians, as Queensland law requires. They’re organised as part of the job, so you don’t need to find your own.

Is a bathroom waterproofed to a standard?

Yes. In Queensland, wet areas are waterproofed to the Australian Standard for wet areas (AS 3740), and the membrane goes to at least 1800 mm high in the shower.

Can I see how much it might cost first?

Yes. The cost guide gives a ballpark in about a minute. Your quote after the measure-up gives the real number, free.

Ready for step one?

Call 0468 511 068, Monday to Friday, 9 am to 5 pm, or send a few details for a free quote.